Deploy & Ops · 3 min read

Commissioning a liquid-cooled rack

Commissioning proves the loop does what the spec sheet promised: pressure-test dry, fill, verify flow and ΔT against the calculated values, prove leak detection, then ramp load. Acceptance is measured numbers against the RFQ, not a handshake.

The sequence

StepWhat happensPass criterion
1 · Dry pressure testLoop pressurized with air/nitrogen before fluidHold specified pressure, zero decay over the stated interval
2 · Fill & purgePG25 (or specified fluid) filled; air bled at high pointsNo visible air in sight glass / flow stabilizes; fluid specs documented
3 · Flow verificationPump at design speed, measure loop flow and supply/return ΔTFlow ≥ design (flow formula); ΔT within design band
4 · Pressure surveyRecord loop ΔP across filter, manifold, UQDsWithin vendor envelope (pressure drop); clean-filter baseline logged
5 · Dew point checkConfirm minimum coolant supply vs room dew point at commissioning and worst-case humiditySupply temperature safely above dew point margin per vendor
6 · Leak system testSensor alarm on simulated leak; interlocks (pump stop, valve, alert) fireDetection announced, response executed, logs captured
7 · Load rampIT load stepped up (e.g., 25/50/75/100%) holding each stepChip and supply temperatures stable at each step; no new ΔP growth
8 · Baseline snapshotRecord all measured values as the reference for maintenanceSigned acceptance against RFQ scope
FIG. 1 — Eight steps from empty pipes to signed acceptance. Steps 3, 5 and 6 are the ones skipped under schedule pressure — and the ones that surface later as incidents.

What "good" looks like in numbers

  • Measured flow within ~5-10% of the calculated value for the actual load and ΔT.
  • Capacity verified at your room temperature, not the 25 °C nameplate point (derating).
  • Every alarm path exercised end-to-end — sensors, pump interlock, remote alert — before the first GPU trains anything.

Related

RFQ scope checklist (write acceptance criteria before buying) · Leaks: risk & response · Maintenance schedule

Sources

Sequence assembled from this site's engineering pages; exact pressures, intervals and margins are vendor- and project-specific — fix them contractually in the RFQ acceptance section.