RFQ scope checklist

Nobody in this segment publishes prices — so quotes are only comparable if the scope is pinned. Send this checklist with every RFQ and require answers in writing; it converts "quote for a liquid cabinet" into twelve defined line items (why prices hide).

#Line itemThe question that pins it
1Capacity @ conditionskW rejected at your room design temp and stated coolant temp — nameplate at 25 °C does not count (derating)
2Heat captureWhat % of IT heat goes to liquid in this configuration; what stays on air (split)
3Facility interfacesPower feeds (kW, redundancy), floor load print (kN/m²), water/none, room AC requirement (1.1×, floor)
4RedundancyPumps N+1? Fans? Controls? What fails how gracefully — and what does the cabinet do on facility power loss
5InterconnectsUQD and manifold spec/version — ORv3 blind-mate or proprietary (UQD, lock-in defense)
6Fluid & warranty termsShipped fluid spec (PG25?), who owns chemistry compliance, what voids the warranty (fluids)
7Monitoring scopeSensors included (flow, ΔP, leak, level, temperature), protocols/BMS integration, alarm routing (leak layers)
8Leak containment & responseDripless couplings, drain/containment capacity, interlock actions on leak detect
9CertificationsCE/UL/IEC 62368-1 Ed.4 and your market's local listing — per-region confirmation in writing (standards)
10Commissioning & acceptanceVendor runs the 8-step commissioning; acceptance = measured flow/ΔT/capacity at your conditions (sequence)
11Service modelResponse SLA, spares on site, maintenance contract scope vs schedule, training for your staff
12Derating documentationCapacity-vs-ambient curve or table in writing — the vendors who can't provide it are telling you something (why)
FIG. 1 — Twelve lines that make two quotes comparable. Items 1, 4 and 12 are where most "mysterious" price gaps live.

How to run it

  • Send the table as a mandatory annex; "see datasheet" is not an answer to item 1 or 12.
  • Score vendors on the comparison table after answers arrive — gaps become visible, e.g. the 20-50 kW turnkey void.
  • Walk the site with the survey checklist before the RFQ so items in line 3 are your numbers, not the vendor's assumptions.

Related

What drives the cost · Cabinet comparison · Standards

Sources

Checklist compiled from this site's engineering pages; each line links the page that explains the underlying physics or standard.